University Bridge Rehabilitation Project

The project will see the bridge closed to the general public from May 1, 2015 to August 30, 2015. A single lane of traffic will remain open for emergency vehicles, Saskatoon Transit buses, Saskatoon Health Region authorized vehicles and school buses contracted by the Saskatoon School Boards only. A system will be implemented that accommodates travel in both directions. A single walkway will also remain open at all times during construction.

A Project Transportation Plan is currently being prepared which involves identification of current and expected traffic delays at 26 key intersections. This information will be used to make improvements, assist with planning detours, and ultimately allow for better movement of traffic in our City.

 

Estimated Project Timeline

The necessary rehabilitation of the iconic bridge is planned for the 2015 construction season.

February 23, 2015 City awards tender to Horseshoe Hill Construction Inc.
May 1 – August 31, 2015 Deck repairs which will impact traffic is expected to occur
August 30 – Sept 15, 2015 Demobilization from site – not expected to impact traffic

 

 

For more details on this project, check out the City of Saskatoon website at the following link:

https://www.saskatoon.ca/moving-around/bridges/university-bridge-rehabilitation-project

Advertisements
No comments yet

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out / Change )

Twitter picture

You are commenting using your Twitter account. Log Out / Change )

Facebook photo

You are commenting using your Facebook account. Log Out / Change )

Google+ photo

You are commenting using your Google+ account. Log Out / Change )

Connecting to %s

%d bloggers like this: